Cross project pouring




 This is the cross 24 hours after the pour. It has been stripped ,cleaned and rubbed to a finish.
 After 5 days the cross will be strong enough to be flipped over. At this time the bottom forms will be stripped off. The front of the cross shown now will be a duplicate of the rear.
 After the forms are removed , this side will then be finished.
 The concrete will be up to 80% of it's total strength after 7 days.




 Concrete is then poured, finished,and let be to start the curing process.